Improving Royal Oak
2020 project map

2020 Construction Projects


Use the map above to see if a project is affecting your street. The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

Copies of construction notice letters are available on the city website here.

CAP1909 MDOT 14 Mile Road Resurfacing

Contractor: Florence Cement Company


Greenfield to Woodward: One lane is open in each direction on the outside lanes of the roadway for Phase III of construction.

Woodward to Crooks: The south half of 14 Mile Road is currently closed for Phase III of construction with traffic shifted to the north side of the roadway. One travel lane is open in each direction.


The contractor is now on the final stage of the project, Phase III. This week the contractor will begin construction of the pedestrian crossing island at Coolidge Highway east of the rail road. They will also paint all the new pavement markings and then open all lanes for traffic. Landscape restoration work will continue on the north side of the roadway.

CAP2003 Downtown Streetscape & Street Lighting Improvements

Contractor: Audia Construction, Inc.


This week the contractor is working at the following locations, removing paver stones and pouring stamped, colored concrete:

  • Third Street, between Main and Center, north side
  • Center Street, between Second and Fifth, east side
  • Second Street, between Center and the alley east of Main, south side
  • Washington Avenue, between Lincoln and Fourth

CAP2010 Water Main Improvements

Contractor: FDM Contracting, Inc.


The city's contractor has been authorized to use the northeast section of VFW Park for construction staging and material storage. The area will be fenced off for public safety. Vehicles will enter/exit using Campbell Road and Sixth Street. Once the project is complete, the disturbed areas will be re-graded and restored with topsoil and seed. The contractor will also make some park improvements by planting new trees and installing new picnic tables.

Fifth Street, S. Rembrandt, S. Altadena - This week the contractor will be adjusting drainage structures and working on landscape restoration before the final layer of pavement is placed.

Seventh Street - The contractor will be working on landscape restoration this week.

S. Vermont Avenue - This week the contractor will be working on concrete replacement of pavement areas and sidewalk ramps. They will also be adjusting drainage structures for the final height of the roadway.

Helene Avenue - The contractor is continuing restoration work this week.

Longfellow Avenue - The contractor will be grading both side of the roadway and prepping for new concrete curbing, pavement base, sidewalks and driveway approaches.

Garbage will be picked up on its regular scheduled day, please have receptacles out by 7:00 a.m.

11 Mile Road - The final water main connection is scheduled for this week. Any affected residents or businesses will be notified via door hanger with the date of the water shut-off and duration. Once complete, pavement restoration will begin.

Farnum Avenue - Work is tentatively scheduled to begin in October. The new water main will be installed via directional drilling and there will be intersection closures at the following locations to allow for water main installation:

  • E. Farnum Avenue & N. Dorchester Avenue intersection
  • E. Farnum Avenue &  N. Kenwood Avenue intersection
Residents on Dorchester Avenue will still be able to enter/exit their block via Forest Avenue to the north and residents of Kenwood Avenue will be able to enter/exit via University Avenue or 11 Mile Road to the south.
CAP2010 project streets list

CAP2015 Asphalt Resurfacing Improvements

Contractor: AJAX Paving Industries


This week the contractor will be continuing work on landscape restoration and punch-list items, weather permitting.

CAP2015 Phases

CAP2035 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc


This week the contractor will work on landscape restoration and punch-list items, weather permitting.

CAP2035 Street list

CAP1941 11 Mile Road and 13 Mile Road
Traffic Signal Improvements

Contractor: Dan's Excavating


11 Mile Road - The contractor will begin installing the mast arm poles for the new signals this week at the Main Street intersection.

13 Mile Road - The contractor will be finishing up at the Crooks Road intersection this week then move to the Benjamin Avenue intersection. Another crew will also be working at the Campbell Road and Rochester Road intersections this week as work progresses.

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2020 project map, find copies of mailed construction notices, and read about the city's various construction projects.