I-75 Freeway & Bridge Work


The following locations are closed this summer for reconstruction as part of the freeway project:

  • 12 Mile Road is closed at I-75
  • Gardenia Ave bridge
  • Lincoln Ave bridge

Questions or concerns regarding the bridge and freeway work should be sent to Oakland Corridor Partners who are overseeing Segment 3 of the construction for MDOT.

Call:    586.486.3626
Email:  info@ocp-i75.com

CAP2109 S Main Street and E Lincoln Avenue Resurfacing

Contractor: AJAX Paving Industries, Inc.


S. Main Street - Lincoln to 11 Mile

This week the contractor will continue working on curb removals, catch basins and the new traffic signal underground work at 3rd, 4th and Lincoln. This will be the focus of work the next couple weeks.

E. Lincoln Avenue - Knowles to Campbell
Work on Lincoln Avenue is tentatively scheduled to begin in May. Construction notices have been mailed and you can view the plans at www.romi.gov/roadwork

CAP2215 Asphalt Resurfacing

Contractor: Hutch Paving, Inc.


Phase 1

Weather permitting, the contractor will continue curb replacements this week, with two crews working concurrently. Crew 1 will continue working on Huron, Dorchester and Kenwood. Crew 2 will be working on Sunnybrook, Jeffrey and Custer, then moving on to Red Run Ct.

Phase 2
If work on Phase 1 streets progresses smoothly, the contractor will begin working on curb removals on Vermont by end of this week or beginning of next week. Delemere has been moved to Phase 2 and work will likely begin next week.

The contractor will work on one side of the street at a time to maintain access for residents during construction. Temporary 'No Parking' signs will be placed where room for equipment is needed.

Table displaying three phases with lists of streets underneath for each phase.

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in PINK & YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2022 project map, find copies of mailed construction notices, and read about the city's various construction projects.