CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
Phase 1
The contractor is finishing up concrete work on Kenwood and Dorchester this week; the contractor plans to mill and pave the roadway beginning next week.
Custer, Jeffrey and Sunnybrook are scheduled to be milled this week on Thursday, with paving to follow tentatively on Saturday or next Monday.
Concrete work is complete on Red Run Ct with the exception of the new intersection pavement. This work is done in halves and expected to be complete by next week.
Phase 2
On Vermont, driveway and curbing removals are complete, as well as the undercutting for the new stone road base and edge drain installation. Intersection work at DeVillen is scheduled for Thursday and Friday. Next week the contractor plans to finish driveway approach installations, install and grade the new stone road base in preparation for paving.
For Delemere, if work progresses smoothly this week, the contractor may begin saw-cutting the pavement in preparation for removals.
Phase 3
Since work has been progressing smoothly, the contractor may be able to start on some Phase 3 streets late next week, such as Alexander, University, Fairgrove and Pingree.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.