Improving Royal Oak

Construction Project Updates


Residents on affected streets will be mailed construction notices in the Spring, prior to work beginning, with detailed information on the project.

The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

2019 Project Map

CAP1908/09 14 Mile Road Resurfacing Improvements

Greenfield Road to Crooks Road

SOCWA Contractor: Verdeterre Contracting, Inc.

City Contractor: Pamar Enterprises, Inc


This project includes work in conjunction with the South Oakland County Water Authority, Michigan Department of Transportation and the Road Commission for Oakland County.

14 Mile Road will be under construction for most of the 2019 construction season, with traffic often limited to one lane in each direction. Motorists are encouraged to find alternate routes during construction, especially during rush hour. For more information regarding the complete scope of the project, visit:
www.romi.gov/14Mile

The week of April 22nd, the city's contractor will continue working installing water main along the south side of 14 Mile Road, primarily near Mankato Avenue and Coolidge Highway.

SOCWA's contractor will continue construction on their water main, primarily working to the east of the rail road bridge.

The current lane closures will remain, with the below restrictions:

  • 14 Mile Road traffic is shifted to the north side lanes of the CN railroad bridge with one lane of travel open in each direction
  • NO LEFT TURNS are allowed onto southbound Coolidge from westbound 14 Mile Road
  • North Coolidge Highway is reduced to one right turn lane and one left turn lane for traffic heading south onto 14 Mile Road
Click on the diagram map below to view the current lane closures.
TC plan 03-25-19
14 Mile map

CAP1935 Road Reconstruction Improvements

Contractor: FDM Contracting Inc.


The city's contractor will be working on Massoit Road and W. Houstonia Avenue the week of April 22nd, starting with the underground utility work.
CAP1935 Street list

CAP1905 Concrete Pavement Repairs

Contractor: Galui Construction Inc.


The contractor tentatively plans to begin mobilizing and saw-cutting the week of April 22nd on the project streets.

CAP1915 Asphalt Resurfacing

Contractor: AJAX Paving Industries Inc


The contractor tentatively plans to begin mobilizing the week of April 22nd. Required tree removals and saw-cutting will begin first. The tentative street order is below.

CAP1915 Phasing

CAP1910 Water Main Improvements

Contractor: FDM Contracting Inc.


The contractor plans to continue water main work on Judson Avenue the week of April 22nd. Once complete they plan to move to Rockingham Road next to begin water main installation.
CAP1910 list of streets

CAP1806 S. Campbell Road Resurfacing

10 Mile Road to 11 Mile Road

Contractor: Iafrate Construction Company


The week of April 22nd, the contractor will continue on the remaining work on S. Campbell Road which includes:

  • installing two pedestrian refuge islands near 6th Street and Brockton/Dallas
  • install the new traffic signals at 4th Street
  • place the permanent road striping on the roadway
  • Complete lawn restoration and punch list items

No lane closures are expected as the contractor will be working within the center turn lane on the pedestrian refuge islands.

You can find more information on the project at romi.gov/campbellroad

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2019 project map, find copies of mailed construction notices, and read about the city's various construction projects.