Improving Royal Oak

Construction Project Updates


Residents on affected streets were mailed construction notices in the Spring with detailed information on the project.

The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

2019 Project Map

CAP1908/09 14 Mile Road Resurfacing Improvements

Greenfield Road to Crooks Road

SOCWA Contractor: Verdeterre Contracting, Inc.

City Contractor: Pamar Enterprises, Inc


This project includes work in conjunction with the South Oakland County Water Authority, Michigan Department of Transportation and the Road Commission for Oakland County. For more information, visit: www.romi.gov/14Mile

SOCWA's contractor has finished working on their portion of the water main project.

The city's contractor will finish pavement restoration the week of June 24th and begin working on landscape restoration.

14 Mile map

CAP1935 Road Reconstruction Improvements

Contractor: FDM Contracting Inc.


The week of June 24th, the city's contractor will finish pavement on the north side of Nakota and begin working on the south side.

The contractor also plans to begin preparing Massoit for pavement.

On W. Houstonia the contractor will continue with concrete restoration work, including curbing and driveway approaches, on the north side of the roadway.

No work is scheduled for the other project streets the week of June 24th.
CAP1935 Street list

CAP1905 Concrete Pavement Repairs

Contractor: Galui Construction Inc.


The contractor plans to continue pavement work on the project streets west of the railroad and the streets south of Normandy the week of June 24th.

If driveway access will be affected, residents will receive a notice via door hanger the day beforehand. The contractor will only work on one side of the street at a time, to maintain access for residents.

CAP1915 Asphalt Resurfacing

Contractor: AJAX Paving Industries Inc


The week of June 24th, the contractor plans to finish all the concrete work on all project streets. The contractor tentatively plans to adjust drainage structures and mill the roadway surface of the remaining project streets, weather permitting, towards the end of the week.

Phase table

CAP1910 Water Main Improvements

Contractor: FDM Contracting Inc.


The week of June 24th, the contractor plans to continue water main installation on Normandy Road west of Coolidge Hwy.

On Rockingham the contractor plans to finish pavement restoration and cleanup.

On Albert Ave, the contractor tentatively plans to connect the new water main at Harvard. Residents will be notified the day beforehand via door hanger if they will be affected by any required water shut-offs.

On Judson Ave, the contractor tentatively plans to work on pavement restoration, towards the end of the week, weather permitting.

No work is scheduled for the other project streets the week of June 24th.
CAP1910 list of streets
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2019 project map, find copies of mailed construction notices, and read about the city's various construction projects.