Improving Royal Oak

Construction Project Updates


Residents on affected streets were mailed construction notices in the Spring with detailed information on the project.

The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project. If you have questions you can contact the Engineering Division at 248.246.3260.

2019 Project Map

CAP1908/09 14 Mile Road Resurfacing Improvements

Greenfield Road to Crooks Road

City Contractor: Pamar Enterprises, Inc


The city's contractor will be finishing restoration work and removing traffic control devices the week of July 8th.


14 MILE ROAD IMPORTANT UPDATE:


The city originally planned to resurface 14 Mile Road from Greenfield Road to Crooks Road this summer, but the contractor bids for the road work were significantly over budget. The city has temporarily cancelled the project and will re-bid the work for spring/summer 2020 construction. The water main projects on 14 Mile Road are now complete, and 14 Mile Road will remain open to traffic until road work resumes next year.

CAP1935 Road Reconstruction Improvements

Contractor: FDM Contracting Inc.


The week of July 8th, the contractor will be working on Massoit Road and Nakota Road. They will be focusing on concrete work, specifically driveway approaches and sidewalk ramps.

The contractor also plans to tie-in the new water main on W. Houstonia Avenue. Any residents affected by the water shut-off will be notified 24 hours in advance via door hanger.
CAP1935 Street list

CAP1905 Concrete Pavement Repairs

Contractor: Galui Construction Inc.


The contractor plans to continue pavement work on the project streets south of 14 Mile Road the week of July 8th.

If driveway access will be affected, residents will receive a notice via door hanger the day beforehand. The contractor will only work on one side of the street at a time, to maintain access for residents.

CAP1915 Asphalt Resurfacing

Contractor: AJAX Paving Industries Inc


The week of July 8th, the contractor will be adjusting sewer structures on the project streets to prepare for the final layer of pavement, which is tentatively scheduled to be placed next week.

Phase table

CAP1910 Water Main Improvements

Contractor: FDM Contracting Inc.


The week of July 8th, the contractor will be working on Albert Avenue and Judson Avenue, preparing the roadways for new pavement.

The contractor will also be testing the newly installed water main on Normandy Road, west of Coolidge Highway.
CAP1910 list of streets
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2019 project map, find copies of mailed construction notices, and read about the city's various construction projects.