CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
Phase 1
Inclement weather this week may delay the schedule, please be advised the below schedule is tentative based on good weather.
On Kenwood and Dorchester, the contractor will be milling the existing pavement this week with paving to follow by end of week.
Paving will be completed on Custer, Jeffrey and Sunnybrook this week.
Concrete work on Red Run Court is mostly completed with milling scheduled for mid-week.
Phase 2
On Vermont, the contractor will be pouring new concrete for the driveway approaches and remaining intersection work. New asphalt pavement is tentatively schedule for the end of the week/beginning of next week.
For Delemere, curbing and pavement removals begin this week.
DELEMERE ROAD CLOSURE AT NAKOTA: Delemere will be closed at Nakota Road to reduce cut-thru traffic and allow for construction operations. The road is open to LOCAL TRAFFIC ONLY. Traffic on Nakota Road can still go east/west through the intersection. The Delemere entrance to Normandy Oaks Park is also closed to reduce traffic. Visitors to the park should use the Nakota Road entrance on the north side of the park.
Phase 3
Since work has been progressing smoothly, the contractor may be able to start on some Phase 3 streets within the month, such as Alexander, University, Fairgrove and Pingree.
*Amelia and Connecticut will be started once the gas work on the block is complete. Consumers Energy Gas company has notified the city they will be starting end of May/beginning of June for the gas work.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.