I-75 Freeway & Bridge Work


The following locations are closed this summer for reconstruction as part of the freeway project:

  • 12 Mile Road is closed at I-75
  • Lincoln Ave bridge

The Gardenia Avenue bridge has now been re-opened to traffic!

Questions or concerns regarding the bridge and freeway work should be sent to Oakland Corridor Partners who are overseeing Segment 3 of the construction for MDOT.

Call:    586.486.3626
Email:  info@ocp-i75.com

CAP2109 S Main Street and E Lincoln Avenue Resurfacing

Contractor: AJAX Paving Industries, Inc.


S. Main Street - Lincoln to 11 Mile

The contractor plans to complete the concrete islands in the center of the roadway this week and has scheduled the final paving of Main Street for next week, Monday and Tuesday.

E. Lincoln Avenue - Knowles to Campbell
The contractor will be finishing up the concrete islands this week and has scheduled the final paving for later next week, likely on Wednesday and Thursday.

You can view the plans at www.romi.gov/roadwork

CAP2215 Asphalt Resurfacing

Contractor: Hutch Paving, Inc.


LANDSCAPE/LAWN RESTORATION: Lawn restoration is being delayed until end of August for more favorable temperatures for seeding.

Phase 1

All the project streets in Phase 1 are complete, with minor restoration work remaining.

Phase 2
For Delemere, the contractor plans to work on restoration this week. They will also schedule the new pavement markings to be placed.

Phase 3
Troy, University, Fairgrove, Pingree an Alexander - Asphalt milling is scheduled to begin the week of the 11th. Once the streets have been milled, the contractor will begin work on adjusting the manhole structures for the final height of the roadway.

Amelia - The contractor is working on curbing and driveway approaches this week between Rochester and Blair. The gas company plans to finish their work this week between Blair and Campbell, so that the city's contractor can begin roadwork starting the week of the 11th.

Connecticut - The contractor will begin staking for the new curbing later this week with curb work scheduled to start the week of the 11th.

Temporary 'No Parking' signs will be placed where room for construction equipment is needed.

Table displaying three phases with lists of streets underneath for each phase.

CAP2110 Northwood Viaduct Pavement Replacement

Contractor: FDM Contracting, Inc.


The city's contractor is connecting the new water main to the water supply system today. Once complete, they will start prepping the road base for restoration.

NORTHWOOD ROAD CLOSURE: Northwood will be completely closed to traffic at the viaduct. The closure will remain in place for several weeks while crews perform construction work. "Road Closed Ahead" signs will be placed along Northwood beginning at Woodward Ave to the west and Crooks Road to the east. However, residents may still see cut-thru traffic in their neighborhood due to the closure.

map showing closure limits

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in PINK & YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2022 project map, find copies of mailed construction notices, and read about the city's various construction projects.