CAP2415/2416 Asphalt Resurfacing
This project will resurface several streets in the residential neighborhoods and the downtown. Work is scheduled to begin in the downtown the week of April 8th. Once the downtown streets are completed the contractor will move to the neighborhood residential streets.
CAP2416 Downtown
Next week the contractor plans to begin work on the streets west of S. Washington, starting on S. Lafayette then working south from Fourth to Seventh Street. Then they will move to the streets east of S. Main, working north to south on Second, Fifth and Sixth Street. The contractor will start with lowering manholes, saw-cutting and performing spot curb removals.
CAP2415 Neighborhoods
Manhole lowering and saw-cutting may happen late next week on S. Pleasant & Edgewood in advance of new storm sewer installation.
Once concrete work is complete on the downtown streets, the contractor will move to the Phase 2 streets beginning with Edgewood, Maple Court and S. Pleasant.
The map below shows the downtown streets to be resurfaced and the table lists all the project streets and phases. The full project map linked above shows the project streets in orange and purple.