CAP2415/2416 Asphalt Resurfacing
This project will resurface several streets in the residential neighborhoods and the downtown.
CAP2416 Downtown
Paving is now complete on the project streets downtown. Only some minor restoration and punch list work still needs to occur.
CAP2415 Neighborhoods
Phase 2: The contractor is adjusting heights and vacuum cleaning sewer structures this week in advance of the final roadway paving. The final layer of asphalt is tentatively scheduled for next week once this work is complete.
Some tree branches were damaged during milling operations, so the Forestry Division will be out to trim the trees once final paving is completed.
Phase 3: Crews plan to complete concrete work on streets this week. Milling of the existing roadways is tentatively scheduled for next week.