CAP2410 Water Main Improvements
On Northwood, the contractor will continue working on pavement removals and pouring new concrete, working easterly from Woodward towards Crooks.
On Sycamore, the contractor will begin concrete removal and replacement, only working on one side of the street at a time. There are also 3 lead water services that still need replacement and are being scheduled with those individual property owners.
If residents will be affected by a water shut off, they will be notified beforehand via doorhanger with the date, start time and duration of the shut off.