CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor will continue water main connections and water service transfers to the new water main during the week of July 10th. Properties that will be without water during connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.
Dallas Avenue
The contractor tentatively plans to begin work on Dallas Avenue the week of July 17th.
Fairview Avenue
The contractor will finish road preparation work once Consumers Energy replaces an existing shallow gas main, likely during the week of July 10th.
Kalama Avenue and Brinkey Avenue
The contractor plans to begin underground utility installations on Kalama Avenue between Brinkey Avenue and Stephenson Highway starting on Monday July 10th. The remainder of the pavement will be removed on Kalama Avenue and Brinkey Avenue after utility work is completed.
Residents will receive door-hanger notices 24 hours in advance when driveways will be unavailable.