CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor tentatively plans to install new curb and gutter along both sides of Batavia Avenue, as well as driveway approaches, beginning Tuesday August 15th. While the concrete cures, the roadway will be milled and the contractor will prepare for the installation of new road base. After the concrete road base has been installed and cured, the contractor will install hot mix asphalt along the entire roadway. The contractor estimates the completion of paving operations by the end of August.
Dallas Avenue
The contractor has finished pipe installation and is working to test the new water main. Minimal site activity is anticipated for the week of August 14th. The contractor tentatively plans to begin water main connections at the end of the week or beginning of the following week.
Fairview Avenue
The contractor will pave Fairview Avenue after Kalama and Brinkey Avenue are paved, tentatively scheduled for the week of August 21st.
Kalama Avenue and Brinkey Avenue
The contractor plans to pave these streets starting on Wednesday August 16th. The pavement will remain closed for one week after concrete is placed to allow for curing. After the road is cured, the contractor will install a pull-off lane along the school property and will also work to install driveways and sidewalk.
Lockwood Avenue
The west half of the roadway has been removed and the contractor plans to begin water main installation during the week of August 14th.