CAP1806 S. Campbell Road Resurfacing
10 Mile Road to 11 Mile Road
Contractor: Iafrate Construction Company
The east half of S. Campbell Road remains closed for the first phase of construction, and traffic is currently shifted to the west side of the road. One lane is open in each direction. The following left turns are not allowed during this phase of construction:
- Northbound and southbound Campbell Road at 11 Mile Road
- Westbound Lincoln Avenue at S. Campbell Road
The contractor plans to pour east side driveway approaches between E. Fourth Street and 11 Mile Road starting on Friday August 17th. The contractor plans to begin milling the asphalt pavement on the east half of the road during the week of August 20th, beginning at 10 Mile Road and working north. The contractor plans to pave the bottom layer of asphalt pavement a few days after milling begins. There will be flaggers in place during paving operations, and drivers should expect additional delays during the week.
You can find more information on the project at romi.gov/campbellroad